Other permits and approvals
If you have any questions or concerns regarding permit requirements, please contact the building department. Our staff are available from 9:00 a.m. to 4:30 p.m., Monday to Friday and will assist you at any point during your construction process.
Demolition Permits
If you propose to demolish any structures occupying an area greater than ten (10) square metres (107 square feet) or part of a structure, you will require a Demolition Permit. An application must be filed with the building department along with a fee. If you are demolishing a building/structure greater than ten (10) square metres you will need to complete a 357 application (application to the council or the assessment review board) which will reduce your tax base accordingly.
Change of Use Permit
If you want to change the way you use all or part of a building, you may require a change of use permit even if you are not planning any construction. Different uses have different Building Code requirements.
Septic System Permits
Applications for new septic system installations, replacements and repairs of all septic systems are submitted to and approved by the building department.
Application and submission information
It is recommended that you contract a licensed installer to help you with the application process as it can be somewhat complicated.
All sewage system permits are to be submitted through your Cloudpermit account.
Applicable fees are to accompany applications, or be received prior to a test hole inspection, which is required for permit issuance.
A sewage permit application must be submitted at the same time as an application for a new dwelling. An application for a review of sewage disposal system must be submitted for any renovations, building additions or additional buildings.
Guest cabins (bunkies) are considered an extra bedroom and will require a review of the current septic system.
Plumbing Permits
A plumbing permit is required for the installation, alteration or repair of drains, water lines and plumbing fixtures. However, if your project involves construction that requires a building permit, the plumbing approval will be incorporated within that permit. If you are hiring a contractor, ensure that the plumber is licensed.
Electrical Permits
Prior to the installation or alteration of electrical equipment you are required to ensure an electrical permit is obtained from the Electrical Safety Authority. A copy of the electrical certificate must be submitted to the building department before receiving an occupancy permit.
Entrance Permits
An entrance permit will be required for any new or revised entrances to a municipal road, county road or provincial highway.
Please visit our Entrance Permits page if you require one for a municipal road. Please contact the County of Haliburton or the Ministry of Transportation for county and provincial roads respectively.